PORT OF TYNE SILOS – NEWCASTLE

CLIENT

Slipform Engineering

N

YEAR

2017

DURATION

20 Weeks

VALUE

£375,000.00

PROJECT DESCRIPTION

 

A project awarded by Slipform Engineering Ltd for the construction of 3no. Reinforced Concrete silos.

This project was highly challenging with a workforce of 50 steel fixers working within a restricted working environment and to a tight work programe.

The construction of each silo consisted of a reinforced steel base and radius walls using a Slip Form System.

KEY FEATURES

 

  • Restricted working environment
  • 24 hours slip form continuous working
  • Accelerated work programme
  • Each silo constructed in 9 days, 24 hour shifts

In

Partnership

With

D’Suza Group HQ

Hi-Spec House
14 Liverpool Road
Warrington
WA5 1EE

D’Suza Group London

1 Northumberland Avenue 
Trafalgar Square 
London
WC2N 5BW

Useful Links:

- Sitemap
- Privacy Policy
- Responsibilities

Contact Us

Phone: 01925 873 235
Email: info@dsuzagroup.co.uk
Registration Number: 10080269

© D'Suza Group 2018 - Powered by Wordpress | D'Suza Group 2018: By D'Suza Group

Pin It on Pinterest